Anticipated WP3 Timeline

1st Quarter

ZONE 2 ROOFING 

  • Zone 1 Roof Continues
  • Zone 2 Roof Commences
  • Apartment Fit Out Continues
  • All Front of House Areas Handed Over/Complete
  • Car Lift Install Continues
  • Back of House Areas ongoing
  • Private Swimming Pools in progress

2nd Quarter

APARTMENTS FIT OUT 

  • Zone 1 Roof Continues
  • Zone 2 Roof Continues
  • Apartment Fit Out Continues
  • Back of House Areas ongoing
  • Plant Rooms Complete

3rd Quarter

COMMUNAL & PRIVATE POOLS 

  • Zone 1 Roof Continues
  • Zone 2 Roof Continues
  • Apartment Fit Out Continues
  • Zone 1 Back of House Areas Complete
  • Communal & Private Swimming Pools Complete