Anticipated WP2 Timeline

1st Quarter

STONE INSTALLATION 

  • Waverton logistics layout established
  • Zone 1 stone facade installed to roof
  • First car lift installed
  • Zone 2 stone commences
  • Commence apartment fit-out

2nd Quarter

ZONE 1 ROOFING 

  • South Audley Street cabins removed
  • Red Lion Yard party wall works commence
  • South Audley Street utilities connections
  • Crystal Gallery envelope commences

3rd Quarter

PERMANENT POWER 

  • Permanent power to Zone 1
  • Zone 2 weathertight up to level 5
  • Crystal Gallery fit-out commences
  • "A" apartments fit-out complete

4th Quarter

APARTMENTS FIT-OUT 

  • All apartments fit-out in progress
  • Spa pool installation complete
  • Townhouse lift installation complete